Go to main contentsGo to main menu
Friday, August 14, 2026 at 4:06 PM

WCSUD bond projects near completion

Project Manager Trevor Truss of E.S. & C.M. Engineers gave the firm’s monthly report to the Walnut Creek SUD board of directors during the May 19 meeting. The current bond projects that are under construction: The surface water treatment plant expansion was contracted at $4.2 million. Due to long lead times, the start date for the project is July of this year.

The 1-million-gallon ground storage tank at the plant site which was contracted at $2.5 million is 95% complete.

One project completely finished is the MG ground storage tank rehab at the plant site which was contracted at $568,607.00.

PLEASE LOG IN FOR PREMIUM CONTENT. Our website requires visitors to log in to view the best local news. Not yet a subscriber? Subscribe today!
Ad
Digital edition access is provided for personal reading use only. Downloading, reproducing, redistributing, archiving, framing, or commercially reselling pages, articles, photographs, or layouts from this publication is prohibited without express written authorization from The Azle News & Springtown Epigraph.